Thank you, Hallsville community, for your unwavering support of our schools! On Wednesday evening, the Board of Education, past and present administration, and HMS cheerleaders participated in the ribbon-cutting ceremony for the new middle school wing.
Superintendent Mr. Walker welcomed guests, stating, "In May 2023, many of you were here for the groundbreaking of the new athletic track and middle school wing. Tonight, 455 days later, we celebrate the official opening of our 15,000-square-foot middle school addition, which includes eight classrooms and a storm shelter."
"This project, completed on time and under budget, is a testament to the dedication of our current and former administration and the unwavering support of our Hallsville community. The Board of Education and I extend our deepest gratitude for your continued commitment to the education and safety of our children."
Board President Bryan Wildenhain also spoke at the ceremony, highlighting the Board’s vision for Hallsville Schools. "The Hallsville School District’s vision is to 'Improve lives through learning.' Every day, our exceptional faculty, staff, and administration strive to uphold this commitment, ensuring every student reaches their potential and becomes productive members of society."
"As our community continues to grow, the Board remains focused on long-range planning to support the future of Hallsville Schools. Today’s ribbon-cutting is the first step in a multi-phase plan to rebuild and enhance our middle school and other district facilities. We are excited to share this journey with you and are committed to keeping our community informed about the progress of these projects. Together, we are truly building our tribe."
We are fortunate to have partnered once again with S. M. Wilson & Co - Construction Managers , our construction management at-risk firm, and Klingner & Associates, P.C. for architecture and engineering services. Their expertise and commitment, as demonstrated in our 2018 & 2022 bond projects, have been instrumental in successfully completing this new addition.
The monthly construction update was provided for the Board of Education to review.
Athletic Complex: The project is complete. SMWilson has scheduled an 11-month warranty walk-through with the District next month.
Middle School: Final inspections are complete, and the district has the final certificate of occupancy.
The monthly update also includes three Change Order Requests the Board approved:
Change Order Request #23: Perform additional work at the Primary School for the completion of the concrete sidewalk project.
Change Order Request #25: This change order is for a credit back to the District for materials used from the previous contractor.
Progress Report #16: August Monthly Update
SMWilson provided their monthly update at the July Board of Education Meeting. The substantial completion date of the middle school addition is Monday, July 22, 2024. During the end of July and August, the district will work on setting up classrooms for the start of the 2024-2025 school year.
Progress Report #15: July Monthly Update
Middle School: The Middle School Addition interior finishes are wrapping up. We have ceilings installed and painting completed. Metal lockers have been installed, and casework and countertops have been installed. Mechanical equipment is being started up, so conditioned air is now operational. The MEP/FP trades are on site for finish trim and Test & Balance. Flooring is almost complete, and the Final Clean is up next.
HMS Current Activities:
Athletic Complex: Barrier fence installation has been held off due to a section of sidewalk that had a deficiency report issued by the materials testing contractor. SMW Team is working to get the concrete replaced and the last barrier fence installed by the middle of July so we do not impact Track & Field activities in Augustilson is working to replace the concrete and the last barrier fence by mid-July so we do not impact Track & Field activities in August.
SMWilson provided their monthly update at the June Board of Education Meeting. The substantial completion date of the middle school addition is Monday, July 22, 2024. During the end of July and August, the district will work on setting up classrooms for the start of the 2024-2025 school year.
Progress Report #14: June Monthly Update
Middle School: The interior finishes continue, as the ceiling grid is installed and the painting is nearly complete. Metal lockers have been installed, and casework and countertops are up next. Mechanical piping is complete, and a system flush is up next. The MEP/FP trades are on site to continue overhead and in-wall trim. Flooring installation began the week of June 24th.
HMS Current Activities:
MEP Overhead Rough: Complete
MEP Equipment Set: Complete
Interior MEP In-wall Rough: Complete
Drywall Finishing: Complete
Painting: 90% complete
Lockers: Complete
Bathroom Partitions: Complete
Ceilings: 90% complete
Casework: 50% complete
Flooring: Installation begins Monday, June 24
Athletic Complex: SMWilson is working to replace the concrete and the last barrier fence by mid-July so we do not impact Track & Field activities in August.
The monthly update includes three approved Change Order Requests :
Change Order Request #20: Credit back to the district per ASI #03 that reduced the brick facade at the west elevation of the new middle school addition
Change Order Request #21: Adding rock to the stadium storm water stilling basins per district request
Change Order Request #22: Removing the gravel drive in the intermediate playground area and installation of a double gate
SMWilson provided their monthly update at the May Board of Education Meeting. The substantial completion date of the middle school addition has been moved from Tuesday, July 16, 2024, to Monday, July 22, 2024. This timeframe will continue to allow the district time to set up classrooms and prepare for the opening of the new wing before the beginning of the 2024-2025 school year.
Progress Report #13: May Monthly Update
Middle School: The roofing system installation and pre-finished metal gutters and downspouts are complete. Drywall installation is complete, and painting is next. Mechanical units have been set. The MEP/FP trades are on site to continue overhead and in-wall trim. The ceiling grid will be installed next.
HMS Current Activities:
Mechanical/Electrical/Plumbing (MEP) Overhead Rough: 95% complete
MEP Equipment Set: 50% complete
Interior MEP In-wall Rough: Complete
Drywall Finishing: 50% complete
Painting: 10% complete
Ceilings: up next
Athletic Complex: The remaining item at the track is the installation of the barrier fence, which has been delayed due to a section of sidewalk that had a deficiency report issued by the materials testing contractor.
SMWilson provided their monthly update at the April Board of Education meeting. One Change Order Request was presented and approved for the relocation of fan coil unit #10 to avoid issues with structural steel. SMWilson reviewed their timeline and progress and confirmed work at the middle school is running on schedule with a substantial completion date of July 16. This timeframe allows the district time to set up classrooms and prepare for the opening of the new wing prior to the beginning of the 2024-2025 school year.
Progress Report #12: April Monthly Update
Athletic Complex: The remaining item at the track is the installation of the barrier fence, which has been delayed due to a section of sidewalk that had a deficiency report issued by the materials testing contractor.
Middle School: The middle school roofing system installation is complete, and the pre-finished metal gutters and downspouts are ongoing. Interior framing is complete, and drywall installation has started. The MEP/FP trades are on site to continue overhead & in wall rough-in. The exterior brick is complete.
HMS Current Activities:
Brick: Complete
Roofing: Complete
Interior Framing: Complete
Interior MEP In-wall Rough: Complete
MEP Overhead Rough: 80% complete
Drywall: 15% complete
Athletic Complex: The remaining item at the track is the installation of the barrier fence, which has been delayed due to a section of sidewalk that had a deficiency report issued by the materials testing contractor. SMWilson Team will work to get as much fence installed prior to the start of Track & Field activities.
Track & Field Current Activities:
Striping - Completed
Barrier Fence - Pending until the section of sidewalk is addressed between the concessions stand and Grandstand.
Middle School: The school's addition roofing system installation is progressing greatly and will be completed this month. The interior framing is nearly complete. The MEP/FP trades are on site to continue overhead rough-in. The exterior brick is 75% complete. Temporary heat is being utilized to keep interior trades moving forward as we continue to see cold temperatures.
HMS Current Activities:
MEP Overhead Rough: 50% complete
Interior Framing: Complete
Interior MEP In-wall Rough: 75% complete
Drywall: up next, material delivered
Exterior vapor barrier: Complete
Brick: 75% complete
Roofing: 75% complete
Additionally, two Change Order Requests were presented and approved. These
included temporary heat through February and the early release of funds. With S.M. Wilson approaching 75% completion of the project, the release of early savings will be returned to the district. SMWilson again attended the meeting and reviewed their timeline and progress. Work at the middle school is running on schedule.
Athletic Complex: The remaining item at the track is the installation of the barrier fence, which has been delayed due to a section of sidewalk that had a deficiency report issued by the materials testing contractor. SMW Team will work to get as much fence installed prior to the start of Track & Field activities.
Track & Field Current Activities:
Middle School: Ironworkers at the middle school addition have completed setting the steel on the building and finalized the detailing work. The MEP/FP trades are on site to continue overhead rough-in. An exterior vapor barrier has been applied to the CMU in preparation for the brick. Exterior framing and interior framing are ongoing. Temporary heat is being utilized to keep interior trades moving forward as we continue to see cold temperatures.
HMS Current Activities:
Additionally, three Change Order Requests were presented and approved. These include minor adjustments to the middle school wing project, including electrical updates in the old central office area and air transfer ducts, diffusers, and air grilles in the new wing HVAC systems. SMWilson again attended the meeting and reviewed their timeline and progress. Work at the middle school is running on schedule.
SMWilson provided the ninth monthly progress report for review at the January Board of Education meeting.
Athletic Complex: Track striping and installation of the barrier fence are the remaining items to wrap up the athletic complex. The striping crew was scheduled for the week of December 18, but had to reschedule because of rain in the forecast. The upcoming forecast with low temperatures and precipitation is making it difficult to schedule the crew. SMW Team is communicating with Byrne & Jones to make sure the striping crew is scheduled as soon as the next break in weather happens. The barrier fence installation has been held off due to a section of the sidewalk that had a deficiency report issued by the materials testing contractor. SMW Team has reviewed this issue with the Klinger Team & Mr. Downs and will finalize the corrective measures the week of 1/15. The timing of the fence installation will then be coordinated with that plan and discussed with the district for final approval.
Track & Field Current Activities:
Middle School: The roof topping slab on the storm shelter was poured in 3 sections, starting on December 19 and finishing on December 22. The carpentry crew was back onsite after the New Year Holiday to strip roof slab forms and handrails. They are currently working on the demo of the eave at the intermediate building in preparation for steel to be set at the Mechanical Room and corridor 117. The ironworkers are installing interior perimeter angles that tie the precast panels to the CMU walls. They will then shift to set the steel framing for the mechanical room and corridor as soon as the weather allows. Now that the topping slab has been poured and temporary window protection is installed, the MEPFP trades are gearing up to start overhead rough-in starting next week.
HMS Current Activities:
Additionally, a Change Order Request to the agreement with Terracon for special testing and inspections was presented and approved. This change is within the budget established for testing and inspections.
SMWilson again attended the meeting and reviewed their timeline and progress. Work at the middle school is running on schedule. Substantial completion of the middle school building addition is scheduled for July 16, 2024.
SMWilson provided the eighth monthly progress report for review at the January Board of Education meeting.
Athletic Complex: The top surface coating at the track started on November 14 and concluded on Friday, December 8. The crew had to work around some weather variables that limited when they could apply, such as temperature, wind, and precipitation. With the top surface complete, the striping crew is scheduled for the week of December 18. In addition to the track surface work, the sidewalk along the west side of the track was completed on November 17, and the backfilling & grading for the area by the concession stand was just completed.
Anticipated Milestone Activities:
Middle School: The masonry contractor has finished laying up the interior CMU walls and the last section of the South elevation exterior wall. The precast setting for the storm shelter lid was completed the week of November 27. The concrete crew has installed forms at the top of the perimeter walls in preparation for the roof slab topping pour. Rebar mat installation is underway, with concrete pours scheduled to start on Tuesday, December 19.
Anticipated Milestone Activities:
SMWilson again attended the meeting and reviewed their timeline and progress. Work at the middle school is running on schedule. Substantial completion of the middle school building addition is scheduled for July 16, 2024.
Progress Report #8: December Monthly Update
SMWilson provided the seventh monthly progress report for review at the November Board of Education meeting.
Athletic Complex: The fence gates, the fence on top of the retaining wall, and the guardrail along the road have been installed. The concrete crew has been pouring the curb for the section of sidewalk along the track near the locker room building. Track surface work started on Tuesday, 11/7. We anticipate the base course of rubber to be completed by Tuesday, 11/14, and then the crew will start the top coat shortly after.
Anticipated Milestone Activities:
Complete Sidewalk North of Grandstand - Started 10/30 - Finish by 11/17
Black Interior Fence - Once the sidewalk along the concession stand/locker room is completed
Track Resurfacing - Start 11/7
Track Striping - crew to be scheduled once the surface course is completed. Note this crew travels throughout the Midwest. Until the surface course is complete, the striping schedule isn’t confirmed.
Middle School: The masonry contractor has been laying up the interior CMU walls. They will be wrapping those up the week of 11/13 and will then button up the last section of the South exterior elevation. Both the electrical and plumbing contractors have been working alongside the masonry crew to get their rough-in conduit and piping installed in the CMU walls. The steel erector will be onsite mid-next week to install steel header beams above the doors at the corridor. The precast setting for the storm shelter lid is scheduled for Monday, 11/27. SMW has held a pre-activity meeting with the steel erector, precast supplier & installer, concrete contractor, and plumbing contractor to discuss upcoming coordination & sequencing of work.
Anticipated Milestone Activities:
CMU Complete - Friday 11/17
Steel Header Beam Install - Wednesday 11/15
Precast Setting - Start Monday 11/27
SMWilson again attended the meeting and reviewed their timeline and progress. Work at the middle school is running on schedule. Substantial completion of the middle school building addition is scheduled for July 16, 2024.
Progress Report #7: November Monthly Update
SMWilson provided the sixth monthly progress report for review at the September Board of Education meeting.
Athletic Complex: The field crew wrapped up the installation on 9/25, and synthetic turf impact testing was completed on 9/27. Hydroseeding on the disturbed topsoil areas outside the track was completed on 10/2. Perimeter fencing is approximately 90% complete. The fence contractor will be back onsite the week of 10/16 to install the permanent gates, fence on top of the retaining wall, and the guardrail along the road. The added sidewalk in front of the grandstand has been poured, and the crew will continue on the section with the integral curb the week of 10/23.
Anticipated Milestone Activities:
Middle School: The second slab section on grade was poured on 9/28. Demolition of openings along the west wall of the existing building was completed so the masonry contractor could complete the west wall. The Masonry contractor then topped out the section half of the north wall, completed the east wall, and moved over to the south wall. They will leave a section out of the south wall and move to the interior walls, working their way out of the building. The electrical contractor is roughing in electrical boxes inside the CMU walls as they are laid and is setting up a temp power panel near the transformer.
Anticipated Milestone Activities:
BOND CONSTRUCTION PROJECT
The monthly construction update was provided for the Board of Education to review.
Athletic Complex: The fence gates, the fence on top of the retaining wall, and the guardrail along the road have been installed. The concrete crew has been pouring the curb for the section of sidewalk along the track near the locker room building. Track surface work started on Tuesday, 11/7. We anticipate the base course of rubber to be completed by Tuesday, 11/14, and then the crew will start the top coat shortly after.
Anticipated Milestone Activities:
Middle School: The masonry contractor has been laying up the interior CMU walls. They will be wrapping those up the week of 11/13 and will then button up the last section of the South exterior elevation. Both the electrical and plumbing contractors have been working alongside the masonry crew to get their rough-in conduit and piping installed in the CMU walls. The steel erector will be onsite mid-next week to install steel header beams above the doors at the corridor. The precast setting for the storm shelter lid is scheduled for Monday, 11/27. SMW has held a pre-activity meeting with the steel erector, precast supplier & installer, concrete contractor, and plumbing contractor to discuss upcoming coordination & sequencing of work.
Anticipated Milestone Activities:
SMWilson again attended the meeting and reviewed their timeline and progress. Work at the middle school is running on schedule. Substantial completion of the middle school building addition is scheduled for July 16, 2024. You can view the entire timeline for each project on pages 25-27.
Progress Report #7: November Monthly Update
Anticipated Milestone Activities:
Middle School: The Ameren Transformer relocation occurred on 8/7. The plumbing contractor has started under slab rough-in. They have extended the sanitary sewer from the science building and connected it to the rough-in at the building pad. Once they are complete, the concrete crew will return to install the interior bearing footings and wrap up the last section of foundations. We expect preparation for slab on grab pours to start the week of 8/21.
Anticipated Milestone Activities:
The monthly update also includes one Change Order Request the Board approved:
Change Order Request #10: Installation of a fence at the stadium complex to restrict spectator access to the track and field event performance areas.
SMWilson was again in attendance at the meeting and reviewed their timeline and progress. Work at the stadium complex and middle school is running on schedule. Substantial completion of the middle school building addition is scheduled for July 16, 2024, and the track and field on October 6, 2023. You can view the entire timeline for each project on pages 25-27.
Athletic Complex: Lime stabilization for the subgrade of the track and field areas was completed the week of 6/19. Laser grading of the field took place the last week of June and wrapped up the week of 7/3. Storm Utility structures are being installed, and the field perimeter drainage system is almost complete. Next week the field crew will be starting the concrete curb between the field and the inside edge of the track.
Middle School: The installation of the 6” water line that runs from the South edge of Hwy 24 to the building has been installed. The concrete footing crew started the week of 6/26 with the footings along the West Elevation. Currently, they are running the North elevation footings and forming/pouring perimeter foundation walls along the West and North.
The monthly update also includes three Change Order Requests the Board approved:
SMWilson was in attendance at the meeting and reviewed their timeline and progress. Work at the stadium complex and middle school is running on schedule. Substantial completion of the middle school building addition is scheduled for July 16, 2024, and the track and field on October 6, 2023. You can view the entire timeline for each project on pages 25-27.
SM Wilson provided the second monthly progress report for review at the board meeting. Earthwork is progressing at the stadium complex, and lime stabilization is scheduled to begin in the coming days. Excavation at the middle school site uncovered at least four undocumented conduits including wiring, so significant additional work has been underway to identify the lines and determine which systems they service. Installation of footings at the middle school site is currently scheduled for the week of June 26. The monthly update includes two Change Order Requests for Board consideration which were approved:
Change Order Request #5: Expansion of the power transformer at the middle school addition to accommodate expansion
Change Order Request #6: Installation of in-grade power distribution to the sideline areas at the football field
SM Wilson provided the first monthly progress report for review at the board meeting. Board action was requested on the following change orders:
1. Change Order Request #3 is the relocation of the transformer and power distribution to service the new middle school wing. This will be paid from the Owner's Contingency.
2. Change Order Request #4 is a voluntary deduction for a change to the roofing material. The credit will be applied to the Owner's Contingency.
SM Wilson is finalizing plans for mobilization and beginning construction at the stadium and middle school. Two change order requests are presented and approved by the Board.
The first is a voluntary credit to the owner's contingency for reducing the length of the artificial turf from 2.25 inches to 2.0 inches. The second is for the coordination and relocation of three district-owned fiberoptic runs in and around the stadium complex. All three lines will be disrupted by construction, and all three lines are needed to maintain current operations. The relocation of the fiberoptic lines is outside the scope of the project as bid and will require the use of the district's contingency funds built into the GMP.
Change Order #1: Synthetic Turk Voluntary Alternate
Change Order #2: Track & Field Fiber
Construction work packages were let for bid at the end of January. SM Wilson evaluated bids and made recommendations to the Board of Education at a special meeting on March 2. At that meeting, the Board approved the selection of bids as recommended by SM Wilson, and voted to move forward with the following: (1) the base bid package, which includes the addition of a middle school wing and the relocation of the athletic track to the stadium complex; and (2) installation of an artificial playing surface at the football field. The GMP amendment was presented for Board approval and approved at the meeting.
The district secured Builder’s Risk insurance for the construction projects this week. Builder’s Risk is provided by MUSIC on projects up to $50,000,000 at no additional cost to its members. The district attorney is coordinating with the water district, the city, Klingner, and SM Wilson on the transfer of a small portion of the water tower parcel to the district, along with a construction easement to allow for the installation of a portion of the athletic track, retaining wall, and fencing near the tower.
Construction work packages were let for bid at the end of January. A pre-bid meeting was held at Hallsville Primary School on February 9, and SMWilson held a bid opening meeting on February 15. SMWilson will now evaluate each bid on multiple criteria and prepare recommendations for the Board of Education. A special meeting will be held in March for bid recommendations along with the Guaranteed Maximum Price (GMP) amendment.
Klingner’s survey team is completing the necessary work to facilitate the transfer of a small amount of real property from the water district to the school district at the north end of the stadium complex. This work includes the setting of points at the new corners, preparing an updated legal description, and preparing a plat of the survey work. Once completed, the district’s attorney will prepare the legal documents for presentation to the water district. The lease financing through Simmons Bank closed on January 31. Funds are now available for use on the project.
The Board approved the final construction documents that will be used in the solicitation of bid packages.
Middle School Drawings-Bidding
Middle School Project Manual
Hallsville Athletic Complex Drawings-Bidding
Hallsville Athletic Complex Project Manual
The district has also encountered a complication on the middle school wing: the city’s water supply is inadequate to deliver the minimum amount of water necessary to meet code on the required fire suppression system. Klingner has engaged the City of Hallsville on this matter, and the Board of Aldermen approved the engagement of Crockett Engineering to perform a feasibility analysis and identify potential options for the delivery of water to the middle school wing location. Crockett understands the urgency of this matter and has begun this process. There are several options available moving forward; district costs will likely be associated with most of these.
In December, the district met with Klingner and SM Wilson to finalize the listing of alternate bids for the project. The final listing of alternates includes several items at the stadium site:
SM Wilson has prepared their second round of construction estimates based on Klingner's design development documents. Estimate totals increased slightly due to the following factors: (1) The middle school wing addition area is up from 15,600 SF to 16,128 SF; (2) the middle school wing addition now includes HVAC controls from Reliable Controls through IFS sole source to match existing controls system; and (3) subcontractor feedback received throughout the Divisions of work, and some estimate values went up slightly from last round. The budget summary and details can be found online.
In addition, the Board approved the winning bid for package #1, precast concrete for the middle school wing, and the Guaranteed Maximum Price (GMP) contract amendment for this specific aspect of the project. Bid package #1 was let in advance of the other bid packages due to the longer lead times for material procurements.
On November 3, the Board held a work session to provide input on the stadium complex design concept and provide direction to the architecture and engineering firm Klingner and Associates on specific alternative designs to complete in preparation for project bidding in 2023. At the regular session meeting, Klinger & Associates presented updated stadium site plans. The Board approved the plans as presented. The final design plans will assist SM Wilson with preparing updated cost estimates and project bidding documents.
Hallsville Track Design & Development Drawings
Hallsville Middle School Design & Development Drawings
Klingner and Associates continue refining the design of the middle school wing and the stadium improvements. The district has provided feedback on both, with some details yet to be determined, particularly regarding the location of structures and event performance areas in and around the stadium complex. The Board of Education will convene a work session to make final decisions on these items, and Klingner will use this information to complete the design development phase. At the conclusion of this phase, SM Wilson will provide updated cost estimates for the project.
The project is currently in the Design Development phase. Klingner and SM Wilson coordinate and confer to ensure the design process continues to fulfill the project scope as articulated by the Board. At the conclusion of the Design Development phase, additional project design documents will be provided to the district for review and feedback, and updated cost estimates will be provided by the construction manager at-risk to guide the Board's decision-making. Design development is expected to conclude by October. The following updates have been provided by Klingner and SM Wilson.
General
Middle School
Stadium Complex
Klingner and Associates presented schematic designs to the Board of Education at the regular meeting on August 17, 2022. Klingner’s principal schematic questions to resolve are the precise location of the athletic track structure, with the Panhandle Eastern pipeline easement to the southeast and the water district tower to the northeast of the stadium. Coordination with both utilities are ongoing.
Also during the August meeting, SM Wilson also provided initial high-level cost estimates for three aspects of the project: the middle school classroom wing, relocation of the athletic track to the stadium complex, and the installation of an artificial playing surface at the football field. The current market construction cost estimates exceed the previous estimates by a significant amount. The Board initiated discussion on potential changes to the project scope and additional potential sources of revenue that might be assigned to the project.
Schematic Design: Middle School
Schematic Design: Football Field
Anti-Discrimination Against Israel Act Certification
At a district facilities work session during the fall semester, the Board of Education requested a quote from Klingner to complete a comprehensive campus boundary survey to be used in future facilities planning, bond issues, and construction. Klingner and Associates’ proposal was presented at the February 16 board meeting and was approved.
Community Forum #3 Presentation
Athletics & Parking Only Approach
A facilities workgroup representing school community stakeholders convened in the spring of 2021 to update the district's facilities master plan. The goals of this group were to review and discuss the status of district facilities and community input, identify additional facility needs, and provide assistance in revising the 2014 Facilities Master Plan. The workgroup presented its findings to the Board of Education in September. You can view their presentation slides here. In April 2022, voters in the Hallsville R-IV School District approved Proposition B, which authorized the issuance of $6,000,000 in general obligation bonds. With over 75% approval, this is the second largest approved bond issuance in the history of the school district. The funds allow the district to continue with its capital improvement plan. During the 2022-2024 construction of a new middle school wing, relocation of the athletic track, and other campus improvements, the district keeps the following three items at the forefront.
A/E services would be completed under the current Agreement with Klingner & Associates, P.C. for the Capital Improvement Program (Primary School Addition) originally executed in September 2018.
A public work session was held at Hallsville Primary School on November 27, 2017. At the session, Superintendent John Downs and representatives from Klingner and Associates presented information on prioritized capital improvement needs. Discussions focused on elementary school expansion to meet the demands of increasing enrollment, the aging middle school, and inadequate athletic track facilities.
The links below include presentation slides and narrative documents regarding these needs. Attendees included community patrons, parents, district faculty and staff, and Board members. Discussions were structured to solicit additional input on capital priorities. Comment sheets were also provided to gather additional feedback.
A second public work session was held at Hallsville Primary School on December 18, 2017. At the session, Superintendent Downs and representatives from Klingner and Associates provided updated information on potential capital improvement projects based on the feedback provided by the community. Discussions focused on additions to the primary school and a phased replacement of the aging middle school building.
The links below include presentation slides and narrative documents on a narrowed listing of potential projects. Attendees again included patrons, parents, faculty and staff, and Board members. Additional discussions were held to gather community feedback on the revised proposals.
On August 20, 2018, the Board of Education approved the purchase of property at 14633 N. Ricketts Road, also known asLot 6 of Key Industrial Park. The property is 1.42 acres and includes an existing 10,800 square foot building. The agreed purchase price is $360,000 with an anticipated closing date of Friday, September 14. The district intends to relocate the facilities and maintenance department to the property. Additionally, space in the building will be used for district storage and an indoor athletic practice facility.
On September 17, 2018, the Board of Education concluded negotiations and approved a contract with Klingner and Associates to provide architectural and engineering (A/E) services for the construction projects under consideration. The firm will commence creation of design documents immediately.
Contract B133
Exhibit A
Exhibit B
Exhibit C
The January 2020 report presented to the board outlined updates on the construction progress for gymnasium and second-grade classroom wing. SMWilson is working to enclose the roofing systems and exterior walls for the gym and classroom additions. Work has continued inside the existing school for the electrical, fire alarm and mechanical systems that feed the new buildings. They are looking forward to the exterior enclosure of the gymnasium and classroom addition in preparation for the interior finish activities. Board action is requested on the following change order: (1) addition of steel angles at brick pilasters, and (2) additional heating units in the second grade wing mezzanine. Additionally, SM Wilson has requested Board approval of pay application #6, also included in the update.
At the district's request, SM Wilson and Klingner have developed estimates for six additional facilities projects identified as priorities by the Board of Education. The estimates were provided for review. Funding available for project completion includes (1) the remaining proceeds from the sale of and premium on the 2018 general obligation bonds, (2) interest income from the investment of bond proceeds, and (3) surplus from the capital projects fund reserve.
Board action is requested on the following change order: (1) updated gymnasium floor graphics, (2) change from oil-based to water-based gym floor sealant, and (3) addition of audio-visual infrastructure in second-grade classrooms. Change orders to the gymnasium floor will allow for summer maintenance to only take 24-48 hours to complete, as opposed to the 9 days it takes now. It will also allow the floor and markings to keep the original color.
Additionally, SM Wilson has requested Board approval of pay application #7, also included in the update. Klingner has reviewed and approved the pay application, and will certify with signature in advance of the Board meeting.
The Board approved two change orders regarding modifications to electrical work and adjustments to network communication equipment as requested by the district to ensure compatibility with existing systems.
Additionally, SM Wilson has requested Board approval of pay application #9, also included in the update. Klingner has reviewed and approved the pay application and will certify with a signature in advance of the Board meeting.
The April 2020 report presented to the board outlined updates on the construction progress for gymnasium and second-grade classroom wing. SMWilson has started interior finishes for both the gymnasium and classroom additions. They are currently working on overhead lighting, HVAC registers, ceiling grid and flooring. Mechanical system start up is in progress and they will continue with temporary heat on the inside of the buildings in preparation for the remainder of the finishes. At this time, the only delay in construction is the fabrication of the gym bleachers. The company responsible is located in Michigan and due to COVID-19 and the state’s strict stay at home orders, the company is currently not producing these items. SMWilson is in weekly communication with the company and is updating any schedules as needed. There are no known delays in the classroom addition.
The board approved two change orders regarding asphalt and landscaping services. These items will be funded with the allowances established by the Board upon adoption of the GMP Amendment, and both came in under the budgeted allotment.
Additionally, SM Wilson has requested Board approval of pay application #9, also included in the update. Klingner has reviewed and approved the pay application and will certify with a signature in advance of the Board meeting.
As the Primary School construction project approaches completion, the construction manager has determined the project is running under budget. During its special meeting on May 11, the Board of Education elected to reduce the GMP to reclaim some of the funds for use on other projects. These funds—along with remaining bond premium, interest income from investment of bond proceeds, and capital projects reserve funds—will be used to complete the following high-priority projects: installation of security cameras and a public address system in the secondary building, partial roof replacement on the high school, and demolition of the old maintenance shop. Board action is requested on the following change orders: (1) Early release of funds to the district (this will result in a reduction to the GMP); (2) Partial re-roofing of the secondary school building; and (3) Demolition of the old maintenance building and site work.
The May 2020 report presented to the board outlined updates on the construction progress for gymnasium and second-grade classroom wing. Work continues for interior finishes for both gymnasium and classroom additions including overhead lighting, HVAC registers, ceiling grid, and flooring. The exterior envelope is wrapping up with final metal fascia and roofing. Site concrete is currently being installed and is near completion. The front canopy at the gym is also now installed. Mechanical system startup is nearly complete and we anticipate gym equipment arriving on-site at the end of the month.
SM Wilson has requested Board approval of pay application #10, also included in the update. Klingner has reviewed and approved the pay application and will certify with a signature in advance of the Board meeting.
As the Primary School construction project approaches completion, the Board of Education elected to reduce the GMP to reclaim some of the funds for use on other projects in May 2020. These funds—along with remaining bond premium, interest income from investment of bond proceeds, and capital projects reserve funds—will be used to complete the following high-priority projects: installation of security cameras and a public address system in the secondary building, partial roof replacement on the high school, and demolition of the old maintenance shop. In a special meeting on June 1, 2020, the board approved a bid for the PA and camera system at the primary and a new public address system at the middle and high school that will tie-in to the phone system upgrades.
The June 2020 report presented to the board outlined updates on the construction progress for gymnasium and second-grade classroom wing. Work continues for interior finishes for both gymnasium and classroom additions. A punch list walk through was scheduled for June 22 witht the School and Design Team. The Life Safety systems have been tested and approved, and landscaping is in process. The gymnasium equipment has also been installed and they are currently working on the flooring system. Board action was requested on the following change orders: (1) Security camera system approved by Board of Education on June 1; (2) public address system approved by Board of Education on June 1; (3) replace grass seeding between the first and second grade wings with rock landscaping (this was a district-initiated change).
Additionally, SM Wilson has requested Board approval of pay application #11, also included in the update. Klingner will review and confirm the accuracy of the pay application. Should Klingner approve the pay application, they will certify with signature in advance of the Board meeting
The August 2020 report presented to the board outlined updates on the construction progress for gymnasium and second-grade classroom wing. Finishing touches to the gymnasium is happening and the building will be turned over to the district. The projects came in under budget and on-time which has allowed the district to allocate funds to additional facilities needs.
These projects include roofing repairs, security cameras, and a public address system at the middle and high school. Board action was requested on the following change orders: (1) Addition of re-roofing angles, (2) Addition of door sweeps, (3) Additional of electric for restroom hand dryers, (4) Masonry repairs at the north gym to address water infiltration, (5) Addition of speakers in high school and middle school restrooms and locker rooms. These were district-initiated items to address a variety of capital issues and safety concerns.
Additionally, SM Wilson has requested Board approval of pay application #13, also included in the update. Klingner has reviewed, approved, and certified the pay application.
The September 2020 report presented to the board outlined updates on the construction progress for various projects around the district. SMWilson has turned all work over to the district including roofing, security camera, and public address system. Final walks with the design team and the district have been conducted, and they are addressing a few final action items.
Board action was requested on the following change orders: (1) Credit for gym equipment, and (2) general conditions for additional projects completed through change orders. At the Board's request, SM Wilson has worked with the subcontractor to secure estimates for additional brickwork to the exterior walls of the north gym. SMWilson will continue moving forward with the additional brickwork.
Additionally, SM Wilson has requested Board approval of pay application #14, also included in the update. Klingner will review, approve, and certify the pay application in advance of Board approval.
The October 2020 report presented to the Board outlined updates on the construction progress for various projects around the district. SMWilson and Klinger continue to work with the district to resolve issues with the security cameras and public address system. The Board approved additional masonry work on the exterior of the north gym and accepted shared savings calculations as applied toward this change order.
Additionally, SM Wilson has requested Board approval of pay application #15, also included in the update. Klingner reviewed, approved, and certified the pay application in advance of Board approval.
As the construction project nears final completion, there were no written updates, no change orders, and no pay application for this month's agenda.
Masonry work at the north gym is still in progress. SM Wilson and Klingner continue to work with the district to resolve the final items related to the security camera and public address systems and to ensure all is functioning as expected.
Klingner & Associates and SM Wilson have provided the following preliminary timeline for project completion. This timeline is subject to change as project development continues.
Architect/engineering design — Through February 2019
Design cost estimating — March through April 2019
Construction document development — Beginning in April 2019
Construction bidding and award — Beginning in May 2019 and ongoing
Primary School construction — May 2019 through June 2020
District takes possession — July 2020